On a fixed-price job, every overrun hour comes out of your margin.

If you quote a fixed price, the client's cost is set and your hours aren't. Here is what an overrun does to your hourly rate.

The short version

On a fixed-price job, the client's price is set. Every hour over your estimate comes out of your margin, not their budget.

Say you quote $20,000 for 100 hours. That's $200 an hour. Run 30% over, and it's $154 an hour.

Price fixed jobs with a buffer, and write change orders for anything outside the scope.

In numbers

A $20,000 fixed-price job
Hours workedYour real hourly rate
100 (as planned)$200.00
110 (10% over)$181.82
130 (30% over)$153.85
150 (50% over)$133.33

Sources

Checked on 19 October 2026.

No law here, just arithmetic: real hourly rate = fixed price ÷ hours worked. Run it on your last fixed-price job.